BUILDING THE BACKBONE OF THE GRID

Transmission Planning

Our long-term roadmap for a reliable, resilient, and efficient transmission system for Nova Scotia

Transmission Planning

Nova Scotia’s electricity transmission system is the network of high-voltage power lines and equipment that moves electricity across the province, delivering power from where it’s generated to where it’s needed.

As our province’s electricity needs change, the transmission system must evolve alongside them. Population growth, economic development, electrification, and the integration of new renewable energy resources all place new demands on the grid.

Through long-term transmission system planning, IESO Nova Scotia works to ensure the transmission system remains reliable, resilient, and capable of meeting the province’s future electricity needs. This includes:

  • Forecasting how electricity demand and power flows may change over time
  • Assessing whether existing transmission infrastructure can meet future needs
  • Identifying potential system constraints and reliability risks
  • Evaluating new technologies and solutions
  • Planning upgrades and expansions to support a growing and changing electricity system
  • Ensuring the transmission system continues to meet applicable reliability standards

By looking years and decades ahead, transmission planning helps ensure electricity can be delivered safely and reliably to Nova Scotians wherever and whenever it is needed.

Information for Industry

The following procedures, agreements, and forms are required to initiate the technical studies and processes necessary for new electricity generation facilities to connect to Nova Scotia’s grid.

Notices

Dates for IESO Nova Scotia’s next cluster study will be announced before the end of 2026.

Notice Date: May 08, 2024

To be eligible for inclusion in the Interconnection System Impact Study stage, and thereby advance the Interconnection Request’s initial Queue Position, the Interconnection Customer must meet the progression milestone requirements of Section 7.2 of the GIP at least ten (10) Business Days prior to the Interconnection System Impact Study commencement date. For clarity, item 7.2 (i) – provision of a detailed stability model for the generator(s) shall mean:

  • Provision of PSSE and PSCAD models in compliance with documents NSPI-TPR-015: PSSE and PSCAD Model Requirements, and
  • Provision of test data demonstrating model testing in compliance with NERC, NPCC and NSPI criteria. NSPI-TPR-014: Model Quality Testing lists the minimum requirements that will be performed by NSPI. Additional testing may be performed to assess compliance with all applicable criteria. Any test not meeting the minimum NSPI requirements will be documented in the MQT report to the IC.

Generator and BESS Interconnection Procedures

These procedures are applicable to transmission systems 69,000 volts and higher.

All completed forms should be sent to:

IESO Nova Scotia
1791 Barrington St.
Suite 1010
Halifax, NS B3J 3K9
Attention: Interconnection Engineer

Interconnection Engineer can be reached at: interconnect@ieso-ns.ca

Bulk Power Interconnection

PSS®E and PSCAD™ Model Requirements

INTERCONNECTION STUDIES

Interconnection Studies

As electricity demand grows, new customers connect to the grid, and renewable energy resources are integrated across the province, the transmission system must continue to evolve. IESO Nova Scotia plans for the reliability and adequacy of the province’s electricity transmission system, including by completing highly technical interconnection studies for new generation or loads—facilities that either produce electricity or consume large amounts of power—looking to connect to the grid. These studies determine if these facilities would have any impact on the grid, or if any upgrades would be required for them to connect.

Generation Interconnection Procedure Study Calendar

Coming soon.

Interconnection Request Queue

Transmission Interconnection Study Reports

Interconnection studies completed for new generation projects are published here as they are completed.

IRCountyMWP.O.IFEASSISFAC
L03Richmond9546C Point Tupper–005–
L01Richmond325L-7011, L-7012–011–
742Guysborough35L-7003–IR742-SISIR742-FAC
686Cumberland340L-8001–IR686-SIS–